One of the first questions we hear from investors is: “Can I even build this legally?” Below we describe what the provision on shelters of up to 35 m² says, what conditions it sets and which documents have to be filed.
The short answer
Since 7 January 2026, a free-standing home shelter with a usable floor area of up to 35 m², intended for the residents of a single-family house, requires a notification with a design instead of a building permit, provided its area of impact lies entirely within the investor’s plot (Art. 29(1)(2a) of the Polish Construction Law). The condition is that the shelter’s area of impact lies entirely within the plot or plots covered by the design. A notification is not filed “with nothing” — a design prepared by a licensed designer is required.
What the provision says exactly
Article 29(1)(2a) of the Construction Law provides that the construction of the following does not require a building permit, but does require a notification:
“free-standing home protective structures with a usable area of up to 35 m² intended to protect the users of a single-family residential building, together with the installations and connections necessary for their use, whose area of impact lies entirely within the plot or plots on which they were designed”.
The provision was added by the Act of 4 December 2025 amending the Construction Law and certain other acts (Dz.U. 2025 item 1847) and has applied since 7 January 2026. Consolidated text: Dz.U. 2026 item 524. The procedure is also described on the website of the Chief Inspectorate of Construction Supervision (GUNB).
Three conditions that must be met at the same time
- the shelter is free-standing and a home shelter (przydomowy),
- it has a usable floor area of up to 35 m² (this is not the building footprint) and serves the users of a single-family residential building,
- its area of impact lies entirely within the plot or plots on which it was designed.
If any of the conditions is not met — for example, the shelter is larger than 35 m², is connected to a building or affects a neighbouring plot — the procedure has to be determined with the designer and the competent authority. Do not assume in advance that a notification is enough.
What the procedure looks like
- Notification with a design. The notification is accompanied by the documents referred to in Art. 33(2)(1)–(4) of the Construction Law (Art. 30(4b)): a site development plan, an architectural and structural design, and a declaration of the right to dispose of the property for construction purposes. Where the plot has no local development plan, a zoning decision may be needed.
- 21 days to object. The architectural and construction administration authority (the starosta) may object by decision within 21 days of service of the notification. Work may start if no objection was raised within that period (Art. 30(5)).
- Before work starts. The investor provides a technical design and appoints a site manager (Art. 42(1)). The structure is subject to geodetic setting-out and as-built survey (Art. 43(1)).
- After construction. The investor notifies the construction supervision authority of the completion of construction; use may begin if the authority raises no objection within 14 days (Art. 54(1)).
For some buildings there is also the investor’s declaration on whether or not an obligation exists to build a protective structure or a temporary shelter place — this concerns buildings listed in Art. 93–95 of the Act on civil protection and civil defence (Art. 33(2)(13) of the Construction Law, as amended by the Act of 17 April 2026, Dz.U. 2026 item 646).
What to prepare for a conversation about the notification
- a map or extract of the plot and information on whether a local development plan applies,
- the planned usable area, the number of people and the position of the shelter in relation to the house and the plot boundaries,
- ground investigation results, if you have them, or information on the groundwater level on the plot.
Each plot and design is assessed by the designer. A notification does not exempt you from meeting the zoning conditions or the local development plan.
See the shelter in 3D and place it in your garden
Rotate the model, tap the points, and on your phone use AR to see the real size of the shelter on your own plot.
Illustrative model. Solutions are tailored to the project and the plot.
AR works on your phone (iPhone: Quick Look, Android: Scene Viewer). On a computer, rotate the model with the mouse.
- 1Reinforced concrete walls 30–40 cm
- 2Mechanical filtered ventilation
- 3Airtight door and vestibule
- 4Cost and permits
Typical investor questions
Does a shelter in the basement of an existing house require a notification? It depends on the scope of the work. Strengthening walls, ventilation and an airtight door may count as construction works or as a change of use. Consult a designer before starting.
Can the authority object? Yes, within 21 days of service of the notification. An objection concerns cases where the notification is incomplete or the design conflicts with the regulations or the local development plan.
How long does the notification procedure take? The period for an objection is 21 days from service of the notification. On top of that comes the time needed to prepare the design, which depends on the design office.
Is a shelter of up to 35 m² always a matter of notification only? No. The notification procedure applies to shelters that meet the three conditions of the provision. Larger structures and shelters inside buildings require a different procedure — the designer determines it.
How Zaremba Construction approaches the formalities
We build according to a design prepared by a licensed designer. We set the scope of the quote after assessing the plot and reviewing the design:
- Preliminary plot assessment — local development plan or zoning conditions, groundwater level, distances from the boundaries,
- Design — we accept a design you already have, or work with design offices,
- Notification — the investor files it; we help establish which documents are missing,
- Excavation — we carry it out with our own excavator,
- Reinforced-concrete structure — built by our reinforced-concrete crew according to the design.
Free quote and plot assessment
Before you commission a design, check whether the plot is suitable for a shelter. Send us the information for a quote or call us.
Phone: +48 696 061 290
Email: info@zarembacs.pl
Article updated: 15 November 2026. Legal status: Polish Construction Law, consolidated text Dz.U. 2026 item 524, and the amendment Dz.U. 2026 item 646; article checked on 15 November 2026. This is general information, not legal advice. Before building, consult the designer and the authority about your design.